Bratislava Hotel: 9,000 m³/h ROTOR ventilation and conference hall cooling

Design, installation, and commissioning of indoor climate systems for the hotel's conference halls after renovation: 9,000 m³/h supply and exhaust ventilation with a rotary heat exchanger, a chiller-fan coil cooling system, and connection to the existing chiller.

Location: Kyiv.Category: commercial

Installation photo report

Routing round and rectangular galvanized-steel air ducts in the ventilation plant room.Photo 01
Process of integrating ventilation ducts into the ceiling void during major renovation at the Bratislava site.Photo 02
Industrial supply and exhaust unit with heat recovery and duct connection nodes.Photo 03
Ceiling air-distribution assembly with round diffusers and linear grilles in the conference hall.Photo 04
Facade of the Bratislava Hotel in Kyiv, where HVAC systems were installed.Photo 05
Technical installation details

Brief execution notes:

For the Bratislava Hotel in Kyiv, design, installation, and commissioning of ventilation and cooling systems for the conference halls after renovation were completed. A 9,000 m³/h supply and exhaust system with a rotary heat exchanger was implemented, as well as a chiller-fan coil cooling system connected to the existing chiller. After installation, air distribution in the rooms was balanced and adjusted.

  • Project: Bratislava Hotel, conference halls after renovation.
  • Location: Kyiv.
  • Ventilation: supply and exhaust, 9,000 m3/h.
  • Heat recovery: rotary heat exchanger.
  • Cooling: chiller-fan coil system.
  • Connection: to existing chiller.
  • Scope: design, installation, commissioning.

Need consultation for your project?